Brief Project Description

chuchle

The Charlotta Masarykova Primary School in Velka Chuchle was tipped out of ten primary schools that faced the urgency to reconstruct their outdated and unsatisfactory heat supply source. Four gas boilers of a total power of 0.375 MWt were installed in the original boiler room. Under the boiler room refurbishment, a Micro T30 CHP unit and two gas boilers of the power of 146 kWt were installed. An accumulation tank of a capacity of 0.8 m3 was installed to provide heat during off- season and to compensate for the disproportion between heat production and consumption.

Installed CHP Unit's Characteristics

Type of the unit Micro T30
Fuel natural gas
Electrical output 30 kW
Heat output 62 kW
Annual heat production 650 GJ
Annual power production 85 000 kW
Year of installation 2011
Place of installation Velká Chuchle

The Benefits of the TEDOM CHP Unit

The boiler room modernization will supply the primary school with  heat at annual cost ranging tens of thousands Czech Crowns lower moreover, the funds saved  can be used for refurbishing the energy source. The school may use the funds for financing higher quality education for its own pupils.